Lesson objective
By the end of this lesson, you can map how requests, work orders, preventive tasks and spare parts flow today, and give each existing data source a verdict: keep, clean or leave behind.
Before you choose software or import anything, you need an honest picture of how maintenance works today: not how the procedure says it works, but how a breakdown is actually reported, handled and closed.
The audit produces two things: a map of the four flows that a CMMS will take over, and a verdict on every data source, so that you know what is worth migrating, what must be cleaned first and what stays behind.
Map the four flows
Follow the four flows one at a time, from the first signal to the last record. Ask the people who do the work and, whenever you can, follow a real case from start to finish.
| Flow | Questions to ask |
|---|---|
| Requests | How does a problem reach maintenance: phone, radio, paper, email, a visit? Who decides what is urgent? How does the requester learn that it is fixed? |
| Work orders | Who assigns jobs, and how? What is written down at the end: cause, time spent, parts used? Where does that record end up? |
| Preventive | Which tasks exist, at what frequency, and who keeps the list? How do you know that a task was done, or skipped? |
| Spare parts | Where are parts stored and listed? How does a technician know that a part is in stock? Who reorders, and when? |
For each flow, write down three things: the tool used (paper, whiteboard, spreadsheet, old software or memory), the people involved, and the points where information gets lost. These losses are the problems the CMMS has to solve, and they connect directly to the goals you set in lesson 1.
Give each data source a verdict
List every place where maintenance data lives today: equipment lists, preventive spreadsheets, work order logs, parts lists, manuals, supplier contacts. Rate each one on three questions: is it complete, is it up to date, and is each item listed only once?
| Verdict | When | What to do |
|---|---|---|
| Keep | Complete, current and without duplicates | Migrate it as it is, after a quick check |
| Clean | Useful, but with duplicates, gaps or mixed formats | Fix it before importing it (lesson 6) |
| Leave behind | Outdated, unreliable or never used | Archive it read-only and do not migrate it |
History deserves its own decision. Years of closed work orders rarely justify the effort of a full migration. A common rule is to migrate only what you will use: open work orders, preventive plans, and a summary of the last twelve months of breakdowns on critical equipment.
Paper, spreadsheet or old software: what you can recover
| Source | What you can usually recover | Typical problems |
|---|---|---|
| Paper and whiteboards | Recent open jobs, the list of recurring tasks | Nothing is searchable, history is partial |
| Spreadsheets | Equipment lists, preventive schedules, parts lists | Duplicates, dates typed as text, several versions of the same file |
| Old software | Equipment, plans, history and parts | Awkward export formats, codes nobody remembers, fields used for something else |
Old software can usually export to CSV or Excel. Ask for a full export early, even before choosing the new tool: some vendors take weeks to provide one, and the contract may limit how long the data stays available after you leave.
Example
The audit at the packaging plant
The audit takes two weeks. By following ten breakdowns from the first call to the restart, the team finds that phone requests reliably reach the whiteboard only when the maintenance manager is on site: at night, about one request in four is never written down.
The preventive spreadsheet lists 180 tasks, but 30 concern machines that were scrapped, and frequencies are written in three different ways. Verdict: clean before import. The equipment list exists in two versions, one from purchasing and one from maintenance, with different names for the same machines: clean and merge.
Five years of paper work orders stay in the archive; only the last twelve months on the two filling lines are summarized. The storekeeper's parts spreadsheet is up to date but contains duplicates. Verdict: clean, and a simple deduplication will do.
Four common mistakes
- Auditing from the procedures instead of watching real cases.
- Asking only managers, never the technicians and operators.
- Deciding to migrate everything, just in case.
- Waiting until the new software is in place to discover the state of the data.
In FreeMaint
Included in Core (free)Use the import templates as a checklist
Every FreeMaint list that can be imported (assets, locations, parts, preventive plans, work orders, requests…) offers a template with the expected columns. Comparing your sources with these templates during the audit shows which fields are missing before anything is migrated.
Read the documentationTemplate for this lesson
Current-state audit checklist
Excel (.xlsx), blank, printable, with automatic verdicts
Key takeaways
- Audit how work really flows, not how the procedure describes it.
- Map four flows: requests, work orders, preventive tasks and spare parts.
- Give each data source a verdict: keep, clean or leave behind.
- Migrate only the history you will use, and archive the rest read-only.