Schedule
Every 3 months
- Fixed calendar: the next date does not move with the completion date.
- Work order window: 7 days
Imported inactive and without equipment: assign it to your assets, set its start date (the first due date), check the intervals against the manufacturer’s manual, then switch it on.
Tasks at each service
Observe the conveyor running, from a safe position
Walk the conveyor while it runs empty then loaded, outside the guards: belt tracking at the head, tail and along the run, spillage, carry-back on the return belt, and the noise of idlers and pulley bearings.
Inspection20 minRisks: Never reach past a guard or touch a moving belt; stay away from the head, tail and take-up nip points.
Inspect the belt and the splice
Conveyor stopped and locked out, check the top and bottom covers, the edges for fraying, and the splice or mechanical fasteners for cracks, lifting and missing fasteners.
Inspection20 minRisks: Isolate and lock out the drive, and release the take-up tension where work requires it, before any contact with the belt.
Inspect the idlers and the return rollers
Look for seized, worn, noisy or missing rollers and bent frames. A seized roller wears through quickly and can start a fire: replace it.
Inspection30 minInspect the pulleys and their lagging
Check the drive, tail and bend pulleys for lagging wear and detachment, material build-up, and their bearing housings for cracks and loose bolts.
Inspection15 minAdjust or replace the belt cleaners and the skirting
Adjust the scraper blades to the belt, replace worn blades, and set the skirting rubbers so they seal without pressing hard on the belt.
Action20 minCheck the belt tension and the take-up travel
Check that the take-up still has travel left in both directions and the belt does not slip on the drive pulley at start-up; shorten the belt if the take-up is at the end of its travel.
Verification10 minGrease the pulley bearings
Grease each pulley bearing with the grease type and quantity given by the manufacturer; never over-grease.
Action15 minTools: Grease gun
Inspect the drive
Check the gearbox oil level and leaks, the coupling or drive chain, the motor and gearbox mounting bolts, and the torque arm where fitted.
Inspection15 minChange the gearbox oil
Once a year, or at the interval given by the gearbox manufacturer for the oil used. Drain warm, inspect the drained oil for metal particles, and refill with the grade and quantity on the nameplate.
Action45 minonce every 4 servicesCheck that every guard is in place before restarting
Check the guards at the head, tail, take-up and bend pulleys and along the drive, then remove the locks.
Verification10 minTest every stop device along the conveyor and record the findings
Pull each pull-cord switch along the full length and press each emergency stop button: the conveyor must stop and stay stopped until reset. Test the belt misalignment switches and the zero-speed switch where fitted. Record the findings and the parts replaced in the work order.
Verification30 min
Parts (indicative)
- Bearing grease cartridge × 1
- Spare carrying idlers, size of the conveyor × 2
Tools (indicative)
- Grease gun
- Infrared thermometer — To find hot idlers and bearings
- Personal lock and tag
Indicative list: on import it is written into the plan’s description, to link to your own inventory.
Reviews
No review yet.
Reviews come from companies that imported this template. Comments are checked before they are shown.
Questions about this template
Licence
Official FreeMaint template, free to use and adapt inside your FreeMaint workspace. An adaptation may be shared in the library under CC BY 4.0; its page then credits this template.
Templates are general guidance. They do not replace the manufacturer’s instructions, your site procedures or applicable regulations.
Equipment: Conveyors
Industries: Manufacturing, Food and beverage, Energy and utilities, Retail
More templates for this equipment
Run these checklists from your phone
Import a template, schedule it on your equipment and record every inspection in FreeMaint. Free, unlimited users.
Use this template in FreeMaintFree your maintenance