Lockout tagout (LOTO) energy isolation procedure
Step-by-step lockout / tagout sequence before maintenance: identify every energy source, isolate, lock and tag, release stored energy, verify zero energy, then restore and re-energise safely.
11 stepsWorkplace safetyVersion 1Updated
This template covers a high-hazard activity. Adapt it to your site’s written procedures, your equipment and local regulations, and have it approved by a competent person before use. When imported, it lands for review: a checklist as a draft, a procedure as inactive.
Free account — copy the procedure into your workspace, or download it as PDF or Excel.
Already have an account? Sign inWhat’s inside
Prepare the job and identify every energy source
Follow your site’s written energy-control procedure for this equipment. List every energy source (electrical, pneumatic, hydraulic, mechanical, thermal, chemical, gravity) and locate each isolation point before touching anything.
Inspection15 minTools: Energy-control procedure, equipment drawings
Risks: A missed energy source is the most common cause of lockout accidents.
Notify affected people
Tell the operators and everyone working in the area that the equipment will be shut down and locked out, why, and for how long.
Action5 minShut the equipment down normally
Stop the equipment with its normal operating controls and stopping sequence, not by opening the isolator under load.
Action5 minIsolate every energy source
Open the disconnects, close the valves and disconnect or block each source identified in step 1. A push-button, selector switch or emergency stop is a control device, never an isolation.
Action15 minTools: List of isolation points, arc-rated PPE
Risks: Arc flash when operating electrical disconnects; wear the PPE required for that switchgear.
Apply personal locks and tags
Each person working on the equipment fits their own lock and tag on every isolation point, or on a group lockbox. The tag shows the name, date and reason.
Action10 minTools: Personal padlocks, danger tags, hasps, breaker and valve lockout devices, group lockbox
Release or restrain stored energy
Bleed residual pressure, discharge capacitors, release or block springs, lower or block raised parts, let flywheels stop and hot or cold parts reach a safe temperature. Fit blocks or pins wherever energy could build up again.
Action15 minTools: Bleed valves, mechanical blocks and pins, discharge tool
Risks: Pressure, springs, gravity and heat can still injure after isolation. Recheck any source that can build up again during the job.
Verify zero energy
With everyone clear, try to start the equipment with its normal controls: nothing must move. Test for absence of voltage with a test instrument proven on a known live source before and after, check that gauges read zero, then return the controls to off.
Verification10 minTools: Voltage tester, proving unit, pressure gauges
Risks: Treat every conductor as live until it has been tested dead.
Carry out the maintenance work
Do the planned work with all locks in place. At a shift change, transfer locks as your procedure requires so that the equipment is never left unprotected.
Action60 minCheck the area and refit guards
Remove tools, materials and blocks, refit every guard and safety device, and confirm the equipment is complete and ready to run.
Inspection10 minAccount for everyone and remove the locks
Make sure everyone is clear of the danger zone. Each lock and tag is removed only by the person who applied it; any other removal follows your site’s exceptional removal procedure.
Action5 minRisks: Never remove another person’s lock.
Notify and re-energise
Tell the affected people that the equipment is about to restart, restore the energy sources in a safe order and confirm normal operation.
Verification10 minRisks: Unexpected movement on restart; keep people out of the danger zone.
Reviews
No review yet.
Reviews come from companies that imported this template. Comments are checked before they are shown.
Questions about this template
Licence
Official FreeMaint template, free to use and adapt inside your FreeMaint workspace. An adaptation may be shared in the library under CC BY 4.0; its page then credits this template.
Templates are general guidance. They do not replace the manufacturer’s instructions, your site procedures or applicable regulations.
Equipment: Workplace safety
Industries: Manufacturing, Food and beverage, Energy and utilities, Facilities
More templates for this equipment
- Inspection checklistOfficial FreeMaintSafety-critical
Portable ladder inspection checklist
Inspection of a step ladder, leaning or extension ladder before use and at each periodic check: labels and rating, stiles, rungs and steps, fixings, feet, spreaders and locks, stability, storage and verdict.
16 checkpointsWorkplace safety
- Inspection checklistOfficial FreeMaint
5S audit checklist for the workplace
5S audit of a production or maintenance area: Sort, Set in order, Shine, Standardize and Sustain, with each criterion graded good, partial or poor to track the area’s progress from one audit to the next.
18 checkpointsWorkplace safety
- ProcedureOfficial FreeMaintSafety-critical
Confined space entry procedure: preparation and permit
Prepare and control a confined space entry: permit, isolation, ventilation, gas testing (oxygen, flammables, toxics), attendant, rescue plan, communication, entry log, continuous monitoring and permit closure.
12 stepsWorkplace safety
Run these checklists from your phone
Import a template, schedule it on your equipment and record every inspection in FreeMaint. Free, unlimited users.
Use this template in FreeMaintFree your maintenance