Checks to complete on each working at height permit: work at height unavoidable, collective protection first, access equipment inspected, fall arrest and rescue plan, fragile surfaces, falling objects, weather, nearby hazards and ground conditions.

15 itemsWorkplace safetyVersion 2Updated

This template covers a high-hazard activity. Adapt it to your site’s written procedures, your equipment and local regulations, and have it approved by a competent person before use. When imported, it lands for review: a checklist as a draft, a procedure as inactive.

Use this template in FreeMaint

Free account: download it as PDF or Excel. Copying HSE checklists into your workspace is included from the Starter plan.

Already have an account? Sign in

What’s inside

Category: Permit — pre-work checklist

  • Permit type: Working at Height
  • Filled in on each permit concerned, before the work starts.

Imported as a draft: it is not used until you review it and click Activate on the HSE template. Once activated, it is used on every new permit of this type and replaces the checklist in use.

Checklist items

  1. Work at height cannot be avoided

    The task cannot be done from the ground, with long-reach tools, or by bringing the item down.

    Pass / FailCritical: a failure blocks the permit
  2. Means of access

    ChoiceRequired
    • Scaffold
    • Mobile elevating work platform
    • Mobile access tower
    • Ladder or stepladder
    • Roof
    • Rope access
    • Other
  3. Working height (m)

    Numberoptional
  4. Collective protection is in place wherever possible

    Guardrails, toe boards, safety nets: they protect everyone without any action from the worker, and come before harnesses.

    Pass / FailCritical: a failure blocks the permit
  5. The access equipment has been inspected

    Scaffold or tower tagged by a competent person; platform pre-use check done by a trained operator; ladder checked and used only for short, light work.

    Pass / FailCritical: a failure blocks the permit
  6. Fall arrest equipment checked, where used

    Harness and lanyard inspected and in date, anchor point rated for fall arrest, and enough clearance below for the arrest. Answer « Pass » if none is used.

    Pass / FailCritical: a failure blocks the permit
  7. A rescue plan exists for a person suspended in a harness

    Rescue within minutes: suspension in a harness quickly becomes dangerous. Equipment and trained people are on site. Answer « Pass » if no fall arrest equipment is used.

    Pass / FailCritical: a failure blocks the permit
  8. Fragile surfaces are identified and protected

    Roof lights, fibre-cement or plastic sheets, ceilings: covered, guarded or marked out, never walked on. Answer « Pass » if there are none.

    Pass / FailCritical: a failure blocks the permit
  9. The area below is cordoned off and falling objects are prevented

    Exclusion zone marked; tools tethered, toe boards or debris netting in place.

    Pass / FailCritical: a failure blocks the permit
  10. Weather conditions allow the work

    Wind below the limit of the platform or the scaffold sheeting, no ice, storm or poor visibility.

    Pass / FailCritical: a failure blocks the permit
  11. Nearby hazards are controlled

    Overhead power lines, moving machinery, vehicle traffic, hot or toxic exhausts: isolated, or kept at a safe distance.

    Pass / FailCritical: a failure blocks the permit
  12. The ground can carry the platform or the scaffold: firm, level, no void or trench

    Answer « Pass » if no platform or scaffold is used.

    Pass / FailCritical: a failure blocks the permit
  13. Workers are trained for the equipment used and fit to work at height

    Pass / FailCritical: a failure blocks the permit
  14. Photo of the access and the protections in place

    Photooptional
  15. Additional precautions or remarks

    Free textoptional

Reviews

No review yet.

Reviews come from companies that imported this template. Comments are checked before they are shown.

Questions about this template

Licence

Official FreeMaint template, free to use and adapt inside your FreeMaint workspace. An adaptation may be shared in the library under CC BY 4.0; its page then credits this template.

Templates are general guidance. They do not replace the manufacturer’s instructions, your site procedures or applicable regulations.

Equipment: Workplace safety

Industries: Construction, Manufacturing, Facilities, Energy and utilities

Run these checklists from your phone

Import a template, schedule it on your equipment and record every inspection in FreeMaint. Free, unlimited users.

Use this template in FreeMaint

Free your maintenance