Corrective Actions

Prevent recurrence

5 min read
Print this section

A corrective action removes the cause of a problem found during an incident or on a failed line of an HSE inspection. Each action has an owner, a due date and a status, and it is closed only after someone has checked that it worked.

Fields

  • Description: what will be done
  • Owner: the person in charge of carrying it out
  • Priority: low, medium, high or critical
  • Due date: an action still open after this date shows as overdue
  • Status: to do, in progress, completed, then closed once verified

Raise an action from a failed inspection line

  1. Open the HSE inspection. Each failed line shows its corrective actions and an "Add corrective action" button; the top of the page counts the failed lines that still have no action.
  2. Describe the action, choose the Owner, a due date and a priority, then save.
  3. To carry the action out as maintenance work, use "Create Work Order" or "Link existing work order" on the action: its labour and costs are then tracked on the work order.

All actions in one place

In the HSE menu, "Action plan" lists the corrective actions of incidents and HSE inspections with their source, owner, due date and status. The tabs "Active", "To do", "To verify" and "Closed" sort them by stage; filter by source, by owner or on overdue actions.

Check effectiveness before closing

When an action is marked as completed, it moves to "To verify". Someone other than its owner then clicks "Verify": "Effective — close the action" closes it with their name and the date, and "Not effective — back to in progress" sends it back to work with a note explaining why. ISO 45001 and ISO 9001 both ask for this check before an action is closed.

Tip

Focus on root causes, not symptoms.

Tip

Equipment inspections keep their own register, under Inspections › Defect findings: a failed point there raises a corrective work order.

Was this page helpful?