Shutdowns
Plan an outage window: gather the work that needs a machine stop, then place it day by day
4 min read
A shutdown is a window during which equipment is stopped on purpose: an annual overhaul, a line changeover, a planned outage. FreeMaint gathers the work that needs the stop in one place and lets you plan it day by day. Shutdowns are part of the Business tier.
Create a shutdown
- Open Shutdowns from the sidebar.
- Create a shutdown: give it a name and its outage window, a start date and an end date.
- Open it to gather and plan the work.
Gather the work
- Work Orders tab → “Add work orders”: pick machines or locations to list the unfinished work flagged “Requires a machine stop” that no outage holds yet, tick it, then “Attach selected”.
- PM Schedules tab → “Add PM schedules”: pull in active PM schedules (“Due during this outage” keeps the ones due in the window), then “Add to this outage”.
- Lockout register tab: the lockouts recorded on the work orders of this outage.
Plan on the Planning tab
Each attached work order is a bar from its planned start to its planned finish, and the “Due date” marker shows its deadline. A work order with no date yet is marked “unplanned”.
- Drag a bar to move it: its duration is kept.
- Drag its left or right edge to change its start or its finish.
- Drop a work order that has no date on a day to plan it.
- With the keyboard, on a selected bar: the arrows move it by one day, Shift + arrow changes its finish.
What re-planning changes
- An open work order becomes scheduled, through its normal status change, recorded in its history.
- A scheduled, in-progress or on-hold work order keeps its status: only its planned dates change.
- The due date never moves. If the new finish passes it, or the bar leaves the outage window, a warning says so.
- A completed, validated, closed or cancelled work order is locked.
- Re-planning needs the permission to update shutdowns and the permission to schedule work orders.
Tip
Set each work order's due date to the deadline the outage gives it: the marker then shows at a glance which work would overrun.