Asset status reflects current operational condition.

Statuses

Operational

Working normally

Degraded

Functional but reduced performance

Down

Not operational, needs repair

Maintenance

Undergoing scheduled maintenance

Standby

Operational but not in use

Retired

Permanently out of service

Who can change the status

  1. Open the asset and click its colored status badge — it becomes a dropdown. There is no separate downtime screen.
  2. Setting the status to Down opens a downtime period; moving it off Down closes that period. These periods make up the asset's downtime history, on its Downtime tab.
  3. Two permissions unlock the badge: "Update assets" is the full right (it also renames, relocates, re-categorizes and retires equipment), while "Report downtime" is the narrow one.
  4. "Report downtime" reaches Operational, Degraded and Down only. An Admin grants it at Organization > Roles.

Tip

Give an operator or a requester "Report downtime" so they can flag a breakdown themselves, without being able to touch the asset registry.

Tip

Keep statuses current for accurate reporting and resource decisions.

Sub-assets

  1. On an asset that has sub-assets, the status window offers "Also apply to its N sub-assets", unticked by default. Sub-assets of sub-assets count too.
  2. Down: its running sub-assets (Operational, Degraded, Standby) stop with it, each with an External stop. Those already Down or in Maintenance keep their own status.
  3. When the asset's stop ends — set back in service by hand, by finishing its work order, or any other way — they restart in the status they had before.
  4. A sub-asset set back in service on its own, or whose stop is made Planned or Unplanned (by hand, by its cause or by a work order), no longer follows: the stop becomes its own.
  5. Any other status is applied once to the sub-assets, with no automatic return.
  6. Retired sub-assets and those you cannot see are never changed. Above 500 sub-assets, use bulk edit from the asset list.

Tip

The parent never restarts by itself when its sub-assets are running: it may be stopped for its own reason.